MoreExchange of morally and physically out-of-date equipment for modern high technological for Valve plant
Company profile – piping, shut-off, regulating, safety ship fittings. Number of employees – 1500.
Plant products: valves, ball valves, dampers, clack valves, regulators, safety valves, etc. Material: stainless steel, bronze, brass, titanium.
Target for "STANKOINVEST" – technical re-equipping.
Project aims: exchange of morally and physically out-of-date equipment for modern high technological, reduction of production costs.
Within the concluded Contract the following works were performed:
- Evaluation of current technological condition of production;
- Calculation of production time norms for standard details using new equipment;
- Calculation of needs for new equipment within the stated production schedule;
- Design of the layout for the new equipment in production work shop of the plant:
- Working out of new technological processes for details production per each unit of new equipment with the selection of new cutting tools;
In the result of executing a complete scope of works according to the contract:
- Were worked out technological processes and CNC for new equipment;
- Were delivered metal cutting and auxiliary tools for the worked out processes;
Achieved results:
After the integration of new production technology was reached reduction of production cost for 30-40%.